broadway expansion updates

 We will continue to provide updates, best routes, and road closures throughout the construction phase. 

Construction Begins Monday January 27, 2020

 

The first phase of construction will begin at Euclid Avenue and stretch through Campbell Avenue. 

Driveways  and sidewalks on the South side will be affected, and will require temporary closures 

throughout the project. Parking may be limited on side streets. Designated bike lanes will be 

unavailable throughout the project duration. Adequate signs and barricades will be 

used to ensure safe travels through the Broadway corridor.


The GOOD NEWS is we are located on the North side of Broadway between Euclid (Park) and Fremont. 

You can still easily access AAPAK Coolstream for all of your A/C parts needs! 

Give us a call and remember we deliver to shops all around the valley.

520-918-3604

UNOBSTRUCTED ACCESS ON NORTH SIDE OF BROADWAY

 

Based upon the current plans there should be mostly unobstructed  access with 3 open lanes on the north side of Broadway for the first 10  months of the project. 

The initial work will primarily occur on the  south side between 

Euclid and Country Club, beginning at Euclid.


The GOOD NEWS is you can still easily access AAPAK Coolstream for all of your A/C parts needs! 

Give us a call and remember we deliver to shops all around the valley. 

520-918-3604

image8

Project Simulated View

 

Well the Broadway Expansion project is officially upon us.  Click on the link below to get a look at the simulated outcome.

image9

january 2020

 This effort will negatively impact so many small businesses on the Sunshine Mile.  For all the hardworking businesses impacted, we would like to thank the loyal Tucson customers for your continued support throughout this expansion project.